Jumat, 11 Mei 2012

Pengecoran lantai II dan Biaya









04 MEI 2012


NO
URAIAN
HARGA SATUAN
TOTAL
1
Besi ø 10 X 550
58,000
31,900,000
2
Besi ø 8 X 110
32,000
3,520,000
3
Triplek 1cm X 155
78,000
12,090,000
4
Semen molen 44m3(k300)
590,000
25,960,000
5
Bambu 2500 Biji
4,500
11,250,000
6
Kayu Glugu 4X6X380 batang
20,000
7,600,000
7
Ongkos tukang
10,000,000
10,000,000
8
Paku 155 Kg
13,000
2,015,000
9
Bendrat 45Kg
15,000
675,000
10
Ongkos tukang Cor Lantai II
15,000,000
15,000,000
11
Sewa Pompa Molen

1,750,000
12
Pasang Listrik

3,425,000
13
Kabel, Paralon dll

2,000,000
TOTAL
127,185,000