PEMBUKUAN BIAYA PEMBANGUNAN GEDUNG SEKOLAH"SITI FATIMAH"
NO TANGGALURAIANDEBETKREDITSALDO
 1     
Kas panti   160,000,000
     160,000,000
 2              Beli sirtu
           885,000      159,115,000
3         besi 400 x 7000 x 19kg
      53,200,000      105,915,000
4      19/01/12tanah uruk 10 truk
        2,250,000      103,665,000
5     
besi 8x100,10x100,12x50,bendrat20kg 
        6,110,000        97,555,000
6     
bata 10.000 bj
        4,700,000        92,855,000
7     
tanah uruk 10 truk kecil
        2,400,000        90,455,000
8              tenaga uruk
           330,000        90,125,000
9      30/01/12UM semen 200 sak
        6,000,000        84,125,000
10    
pasir dan bata
        4,100,000        80,025,000
11     4/2/2012bayar tukang
        4,000,000        76,025,000
12            kusen pintu 3 buah
        4,350,000        71,675,000
13     8/2/2012jendela
        3,600,000        68,075,000
14    
sisa bayar semen 200 sak
        1,125,000        66,950,000
15    
sirap randu 6000x200
        1,200,000        65,750,000
16     19/02/12pasir   
        3,750,000        62,000,000
17    
12 dumtruck X 750.000
        9,000,000
       53,000,000

18    
ongkos krj tahap 3
        2,500,000
       50,500,000

19    
ongkos krj tahap2
        2,000,000
       48,500,000

20    
koral 1 truck
           900,000
       47,600,000

21     24/02/12sirtu
        3,750,000
       43,850,000

22    
kayu sirap10bendel 3x4,10bendel4x6
        2,830,000
       41,020,000

23     26/02/12bayar tukang
        5,060,000
       35,960,000

24     27/02/12sirtu
        5,250,000
       30,710,000

25     28/02/12koral+ timba
        5,270,000
       25,440,000

26    
bata 7000 bj
        3,290,000
       22,150,000

27     5/3/2012kerikil
           950,000
       21,200,000

28     7/3/2012UM besi 10x200
        7,000,000
       14,200,000

29    
bayar tukang
      11,500,000
         2,700,000


  160,000,000
    157,300,000
   
         2,700,000


MATERIAL YANG MASIH DIPERLUKAN


NO
URAIAN
SATUAN HARGA
TOTAL
1
Besi ø 10 X 350
58,000
20,300,000
2
Besi ø 8 X 100
32,000
3,200,000
3
Triplek 1cm X 130
78,000
10,140,000
4
Semen molen 34m3
62,000
21,080,000
5
Bambu 2000 Biji
4,500
9,000,000
6
Kayu Glugu 6X6X200 batang
20,000
4,000,000
7
Ongkos tukang kurang
10,000,000
10,000,000
8
Paku 60 Kg
11,000
660,000
9
Bendrat 20Kg
15,000
300,000
10
Ongkos tukang Cor Lantai II
15,000,000
15,000,000

93,680,000


















NB : Kami Masih mempunyai Tanggungan ke Toko Matrial dan Perorangan