NO | TANGGAL | URAIAN | DEBET | KREDIT | SALDO |
|
1 |
| Kas panti | 160,000,000 |
| 160,000,000 |
|
2 | | Beli sirtu |
| 885,000 | 159,115,000 |
|
3 | | besi 400 x 7000 x
19kg |
| 53,200,000 | 105,915,000 |
|
4 | 19/01/12 | tanah uruk 10 truk |
| 2,250,000 | 103,665,000 |
|
5 |
| besi 8x100,10x100,12x50,bendrat20kg |
| 6,110,000 | 97,555,000 |
|
6 |
| bata 10.000 bj |
| 4,700,000 | 92,855,000 |
|
7 |
| tanah uruk 10 truk kecil |
| 2,400,000 | 90,455,000 |
|
8 | | tenaga uruk |
| 330,000 | 90,125,000 |
|
9 | 30/01/12 | UM semen 200 sak |
| 6,000,000 | 84,125,000 |
|
10 |
| pasir dan bata |
| 4,100,000 | 80,025,000 |
|
11 | 4/2/2012 | bayar tukang |
| 4,000,000 | 76,025,000 |
|
12 | | kusen pintu 3 buah |
| 4,350,000 | 71,675,000 |
|
13 | 8/2/2012 | jendela |
| 3,600,000 | 68,075,000 |
|
14 |
| sisa bayar semen 200 sak |
| 1,125,000 | 66,950,000 |
|
15 |
| sirap randu 6000x200 |
| 1,200,000 | 65,750,000 |
|
16 | 19/02/12 | pasir |
| 3,750,000 | 62,000,000 |
|
17 |
| 12 dumtruck X 750.000 |
| 9,000,000 |
|
|
18 |
| ongkos krj tahap 3 |
| 2,500,000 |
|
|
19 |
| ongkos krj tahap2 |
| 2,000,000 |
|
|
20 |
| koral 1 truck |
| 900,000 |
|
|
21 | 24/02/12 | sirtu |
| 3,750,000 |
|
|
22 |
| kayu sirap10bendel 3x4,10bendel4x6 |
| 2,830,000 |
|
|
23 | 26/02/12 | bayar tukang |
| 5,060,000 |
|
|
24 | 27/02/12 | sirtu |
| 5,250,000 |
|
|
25 | 28/02/12 | koral+ timba |
| 5,270,000 |
|
|
26 |
| bata 7000 bj |
| 3,290,000 |
|
|
27 | 5/3/2012 | kerikil |
| 950,000 |
|
|
28 | 7/3/2012 | UM besi 10x200 |
| 7,000,000 |
|
|
29 |
| bayar tukang |
| 11,500,000 |
|
|
| 160,000,000 |
|
|
|
MATERIAL YANG MASIH DIPERLUKAN
NO
|
URAIAN
|
SATUAN HARGA
|
TOTAL
|
1
|
Besi ø 10 X 350
|
58,000
|
20,300,000
|
2
|
Besi ø 8 X 100
|
32,000
|
3,200,000
|
3
|
Triplek 1cm X 130
|
78,000
|
10,140,000
|
4
|
Semen molen 34m3
|
62,000
|
21,080,000
|
5
|
Bambu 2000 Biji
|
4,500
|
9,000,000
|
6
|
Kayu Glugu 6X6X200 batang
|
20,000
|
4,000,000
|
7
|
Ongkos tukang kurang
|
10,000,000
|
10,000,000
|
8
|
Paku 60 Kg
|
11,000
|
660,000
|
9
|
Bendrat 20Kg
|
15,000
|
300,000
|
10
|
Ongkos tukang Cor Lantai II
|
15,000,000
|
15,000,000
|
|
93,680,000
|
|
|
|
|
|
|
|
|